Project Overview
Two-hundred and twenty-two solar panels have been installed at the Animal Shelter
The Medical Examiner’s Office is currently having 488 solar panels installed. Roof repairs on the Harvard Road Garage are currently being conducted, then 1,948 panels will be installed.
All installations should be completed by Spring 2020. The solar panels are expected to yield a total of 1,147,000 kwh of energy. The panels would account for 13 percent of the total load for the Animal Shelter, three percent for the Medical Examiner’s Office and 25-30 percent for the Harvard Road Garage.